June 4, 2008
Update on progress.
In the last week, the long delay due to making the sanitary line fit between two water lines, a gas line and a million pair ATT fiber optic trunk line has not only been resolved, but the actual sanitary line is now in place. This part of the work is complete. The site contractor , Ron Chambers, anticipates placing curbs in three weeks as he will have completed on site underground by then. He stated that the roads will follow over the next three weeks after the curbs. This means the roads will be in within six weeks.
Mr. Hanselman, an architect/builder, is building a very nice, very green home on lot 22. His project is underway. Robert tells me that he will “go vertical” next week. His footings are being done now. We will be seeing a lot of activity at Campo Verde as a result.
Our site contractor informed me that he can maintain access to lots for builders, as he is doing for Mr. Hanselman. We invite those considering a lot purchase to keep this in mind, as we see no reason to not get a good start on new homes now.